In order to
complete the monumental task of constructing the 2,770km Overland
Telegraph line within the 18 month time limit, the project was
subdivided into 4 sections:
The Northern
Section was to be completed by private contractors Joseph Darwent
and William Dalwood and spanned 960km from Darwin
to Tennant Creek. The
contactors however, made it only as far as the Katherine River before
floods, bogged-down horses and spoiled food took their toll and
many of the construction party refused to work any further in the
harsh tropical conditions. Todd
sacked the contractors and a government party took over, completing
the construction of the line from Katherine