SOUTHERN SECTION
Northern
Section | North Central Section
| Central Section
In order to
complete the monumental task of constructing the 2,770km Overland
Telegraph line within the 18 month time limit, the project was
subdivided into 4 sections:
The Southern
Section of the line was put out to a private contractor, Edward
Meade Bagot, and covered 816km of mostly pastoral country from Port
Augusta to the Macumba River near Oodnadatta.
|